Pictures showing the completion of the concrete road to the ring road. Guttering to be completed before the end of June.
15th May - 15th Jun 05 Completion of the concrete road to the ring road
More pictures showing the Angthong Hills high quality/finish concrete road
15th Apr - 15th May 05 Preparing the Government road
Clearing of the government road, to enable the process of completing the concrete road.
1st Apr - 29th Apr 05 Pictures of the internal concrete road
Picture 1 is of plot 19. Picture 2 is of plot 20. Picture 3 is of plot 21 & 25 Picture 4 is of plots 24,23,22
16th Mar - 24th Mar 05 Plots 1-25 Concrete Road Access is now completed
The completion date for the Internal roads is expected around the end of April 2005
1st Mar - 9th May 05 Final Subdivision
All Plots have now be sub-divided and come with individual land title.
1st Mar - 15th Mar 05 Concrete Road due for early completion
More pictures showing continued progress
15th Feb - 28th Feb 05 Progress of Concrete road
More pictures showing the rapid progress of the concrete road
1st Dec 04 - 31st Jan 05 Delay on infrastructure
This was due to the Land office taking considerable time to sub-divide the land. This however has now been completed hence the concrete road has commenced.
20th Nov - 23rd Nov 04 Further Development Updates
Pictures of Infrastructure already in place
15th Nov - 23rd Nov 04 Latest Development Updates
More detailed pictures showing the infrastructure already in place
8th Nov - 23rd Nov 04 Further pictures showing completion of Electricity and water supply
Further pictures showing the rapid progression of the high quality infrastructure being put in place.
1st Nov - 23rd Nov 04 Completion of Water & Three Phase Underground Electricity
The 3 phase underground electricity and 2 deep water wells has now been completed. This was completed 1 week ahead of schedule.
1st Oct - 30th Nov 04 Water & Three Phase Underground Electricity being put in place
At the present moment, considerable infrastructure is being put in place including 3 phrase underground electricity and 2 deep water wells. This will give every plot a continued water and electric supply. This is due for completion by the end of November.
15th Sep - 20th Sep 04 Planting of 400 trees and plants
The Angthong Hills estate will benefit from the planting of 400 trees these include coconut trees which will line the road leading into the land. Numerous Banana, Palm Oil and Beetlenut have also been planted.
1st Aug - 30th Sep 04 Creating of roads throughout the land, and Marketing begins
The next step on the Angthong Hills Project was to split the plots up by way of a 5 metre dirt road within the land. This also included a 6 metre dirt road all the way from the concrete road that leads off Koh Samui?s ring road. Diggers worked tirelessly for 2 weeks to complete the road system.
1st Jul - 31st Jul 04 Planning and Obtaining further professional advice
At this point we applied/obtained sub division of the title deed. Professionals including Architects & building constructors gave us professional advice on the size of each plot ideal for this spectacular seaview land. Only 31 plots were decided this ensured that each plot was of a substantial size. Please see plot map.
9th Jun - 30th Jun 04 Clearing of the Land and Survey of the Land
At the beginning of June 2004 (just after Angthong Hills Ltd had purchased the land). The clearing of the land commenced. This envolved clearing all small trees/shrubs from the land. This also enabled the Land Office to survey the land accurately.